Outpatient Modular MRI/CT Building
Shands Hospital
Jacksonville, Florida

 

   
       
  Hardee
Project Description:


  • 8 Modular Units totaling 5,300 s.f. medical space housing the most advanced Siemens MRI and CT diagnostic equipment.
  • The facility was fully operational and accepting patients in only four months after work started.
  • The modular components were custom fabricated off-site and trucked over-the-road to the site where they were off-loaded and set in place using a 550 ton crane.
  • Each unit was specially constructed utilizing a heavy tube steel skeleton with concrete floors and a steel roof deck to hold up to the extreme loading associated with shipping and handling as well as the weight of the new medical equipment.
  • Special features included copper RF shielding for the MRI, lead shielding for the CT,┬ácomplete emergency generator backup power, medical gases, and redundant cooling systems.
  • Maintained a safe site throughout construction with no injuries or incidents.
  • General Contractor
 
       
 